  • Transportation Commission — Wednesday, April 29, 2026 · from the brief

    Sidewalk Projects Update. Staff gave a status update on three 2026 sidewalk projects: the Sheridan Hills Safe Routes to School project (contract awarded April 28, construction June 8-September 25, 2026); the 73rd Street…

    Open this meeting's brief Source document

  • Transportation Commission — Wednesday, July 1, 2026 · from the brief

    Approval of April 29, 2026 Transportation Commission Minutes. The Commission was scheduled to approve minutes from its April 29, 2026 meeting, which covered the Nicollet Avenue construction preview, Penn Avenue Open…

    Open this meeting's brief Source document

  • City Council — Wednesday, June 5, 2024 · from the brief

    Project Updates: Sidewalk and Street Improvements. Transportation Engineer Hardegger reported that sidewalk construction on 71st Street outside STEM/RDLS was set to begin in mid-June 2024, with pedestrian ramp…

    Open this meeting's brief Source document

  • Transportation Commission — Wednesday, April 1, 2026 · from the brief

    City Staff, City Council, and Liaison Updates. City staff gave construction updates on Nicollet Avenue, I-494, Highway 77, the Sheridan Hills Safe Routes to School project, and Metro Transit Route 14 stop changes, plus…

    Open this meeting's brief Source document

  • Transportation Commission · Wednesday, April 29, 2026

    neer Department Director: Kristin Asher, Public Works Director Item for Consideration: Sidewalk Projects Update EXECUTIVE SUMMARY Staff will be providing a schedule and design update for the three 2026 sidewalk projects…

    Open this meeting's brief Source document

  • City Council · Tuesday, November 25, 2025

    OE D D S D c Bolton & Menk, Inc. 2025, All Rights Reserved H:\RICH\25X139183000\CAD\C3D\MISC_139183_Layout 1.dwg 10/23/2025 10:06:35 AM R Sidewalk Project - Sheridan Hills City of Richfield, Minnesota Figure 1: Sheridan…

    Open this meeting's brief Source document

  • City Council · Tuesday, July 22, 2025

    will all follow a truncated version of the city's Public Engagement Process for Street Reconstruction Projects. Staff are proposing a series of open houses along the project corridors to meet with residents in the…

    Open this meeting's brief Source document

  • City Council · Tuesday, December 9, 2025

    cts, which will add approximately 2 miles of new sidewalk facilities with a combined investment of about $2.9 million. He reported that engagement included mailers, surveys, pop-up events, an open house, and an online…

    Open this meeting's brief Source document

  • Work Session · Tuesday, August 12, 2025

    3 (Lyndale Ave) to CSAH 35 (Portland Ave). The new sidewalk will be separated from the roadway by a boulevard, and new ADA-compliant curb ramps will be added throughout the corridor. A new ADA-compliant at-grade…