Work SessionTuesday, October 14, 2025

1 item on the record

Read this day's brief Official records (city portal)

Items on the record

  1. Item 2Discussedinformational or procedural item — no vote taken

    I-494 Phase 2 Corridor Project Update

    City Engineer Joe Powers and MnDOT staff presented an update on Project 2 of the I-494 Corridor Vision, covering the municipal consent process, project schedule, and construction anticipated to begin in 2027. Richfield's estimated local cost share is $9,000 for lighting and engineering contingencies, and MnDOT reviewed noise, air quality, and greenhouse gas analysis findings. No formal action was taken; MnDOT agreed to follow up with additional information after council questions.